SSC GD 2023 PYQ — Question 59

SSC GD Constable (English) - 27 Jan 2023 - Shift 2 • Quantitative Aptitude • Q59

Sanju can do a piece of work in 17 days, and Rohan can do the same work in 68 days. Find the time required to complete the same work if they are working on alternate days and Sanju starts the work on the first day

Show answer & explanation

Correct answer: B

Explanation

The Correct answer is option 2 i.e.107/4 days

Given that

Sanju can do a piece of work in 17 days 

Rohan can do a piece of work in 68 days

Total work = LCM (17, 68) = 68

The efficiency of Sanju = 68/17 = 4

The efficiency of Rohan = 68/68 = 1

if they are working on alternate days and Sanju starts the work on the first day

In 2 days, work = 1 + 4 = 5

In 26 days, they complete the work = 5× 13 = 65

Remaining 3 work is done by Sanju in 3/4 days 

Hence, the time to complete work in =  26 + 3/4 = 107/4 days