SSC GD 2019 PYQ — Question 71

SSC GD Constable (English) - 14 Feb 2019 Shift 3 • Quantitative Aptitude • Q71

Rohit, Mohit and Sumit individualy can complete a work in 8 days, 14 days and 21 days respectively. In how many days these three together can complete the same work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 168/41 days.

Understanding/Application

Let total work to be done be L.C.M.(8,14,21) = 168 units

Rohit complete work in 8 days.

Rohit's efficiency = 168/8 = 21 units/day

Mohit's efficiency = 168/14 = 12 units/day

Sumit's efficiency = 168/21 = 8 units/day

Total work done by them in 1 day together = (21 + 12 + 8) = 41 units/day

Time taken by them to complete 168 units of work = 168/41 days