SSC MTS 2023 PYQ — Question 14

SSC MTS - 08 May 2023 - Shift 1 • Quantitative Aptitude • Q14

Rohan alone can do a work in 10 days and Mohan alone can do the same work in 15 days. In how many days will they together complete the same work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 6 days.

Rohan can complete the work in = 10 days

Rohan's work rate = 1/10

Mohan can complete the work in = 15 days

Mohan's work rate = 1/15

Combined work rate = 1/10 + 1/15

⇒ 3+230=5/30=1/6\frac{3+2}{30} = 5/30 =1/6 per day

The time taken to complete the work together is = 1/Combined work rate

⇒ 1/(1/6) = 6 days