SSC GD 2023 PYQ — Question 44

SSC GD Constable (English) - 17 Jan 2023 - Shift 4 • Quantitative Aptitude • Q44

Riya can complete a piece of work in 12 days, Reeta in 18 days and Geeta in 24 days. Reeta and Geeta worked together for 6 days and then Geeta was replaced by Riya. In how many days altogether was the work completed?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 9 days

As we know that

Worker × time = Total work

Given that

Riya can do a work in 12 days

Reeta can do a work in 18 days

Geeta can do a piece of work in 24 days

Total work = LCM (12, 18, 24) = 72

The efficiencies of Riya, Reeta and Geeta are

⇒ (72/12 = 6), (72/18 = 4), and (72/24 = 3)

According to the question

⇒ (Reeta + Geeta) × 6 + (Reeta + Riya) × d = 72

⇒ (4 + 3) × 6 + (4 + 6) × d = 72

⇒ 42 + 10d =72

⇒ 10d = 30

⇒ d = 3 days

Hence, the work is completed altogether in 6 + 3 = 9 days