Richa, Rita and Reena can independently complete a work in 8 hours, 12 hours and 24 hours, respectively. If they work together, how much time will they take to complete that work?
Show answer & explanation
Correct answer: A
Explanation
The correct answer is option 1 i.e. 4 hours.
Richa can complete the work in = 8 hours
so her work rate is = 1/8 per hour.
Rita can complete the work in 12 hours
so her work rate is = 1/12 per hour.
Reena can complete the work in 24 hours
so her work rate is = 1/24 per hour.
Combined work rate = 1/8 + 1/12 + 1/24 = = =
Richa Rita and Reena can complete the work in = 4 hours