SSC CGL 2023 PYQ — Question 70

SSC CGL - 21 July 2023 - Shift 3 • Quantitative Aptitude • Q70

Rekha alone can complete a work in 16 days, and Bina alone can complete the same work in 12 days. Starting with Rekha, they work on alternate days. The total work will be completed in:

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 1334\frac{3}{4} days.

Let the total work of 16 and 12 days is = 48 units (LCM of 16 and 12)

The efficiency of Rekha is = 48 / 16 = 3 units

The efficiency of Bina is  = 48 / 12 = 4 units

Total work done in 2 days = 3 + 4 = 7 units

42 units of work done by Rekha and Bina = 6 × 2 = 12 days

Rekha does in 1 day  = 3 units

Bina does  in 1 day  = 4 units

Hence

Bina does 3 units in = 3/4 days

Total number of days = 12 + 1 + 3/4 = 1334\frac{3}{4}days