SSC GD Constable (English) - 1 Feb 2023 - Shift 3 • Quantitative Aptitude • Q59

Reeta can do a piece of work in 14 days and Geeta can do the same work in 21 days. How many days Reeta and Geeta take together to complete the same work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 8.4.

Reeta can do a piece of work in 14 days and Geeta can do the same work in 21 days

L.C.M(14 and 21) = 42

The efficiency of Reeta = 42/14 = 3 units

The efficiency of Geeta = 42/21 = 2 units

Time taken by both = 42/5 = 8.4 days