SSC GD 2023 PYQ — Question 60

SSC GD Constable (English) - 25 Jan 2023 - Shift 4 • Quantitative Aptitude • Q60

Ravi and Sumant can complete a piece of work in 40 and 50 days, respectively. If they work at it on alternate days starting with Ravi on the first day, in how many days will the work get over?

Show answer & explanation

Correct answer: D

Explanation

The Correct answer is Option 4 i.e.  4425\frac{2}{5}.

Ravi and Sumant can complete a piece of work in 40 and 50 days

L.C.M(40 and 50) = 200

The efficiency of Ravi = 200/40 = 5 units

The efficiency of Sumant = 200/50 = 4 units

Starting from Ravi

2 days = 9 units (multiplied by 20)

2 × 20 = 9 × 20

40 days = 180 units

41 days = 185 units

42 days = 189 units

43 days = 194 units

44 days = 199 units

Remaining work = 200 - 199 = 1 unit

So, the work will be completed in  4425\frac{2}{5} days