SSC GD 2023 PYQ — Question 53

SSC GD Constable (English) - 31 Jan 2023 - Shift 3 • Quantitative Aptitude • Q53

Ramesh and Suresh can complete a piece of work in 10 days and 12 days, respectively. If they are working on alternate days, starting with Ramesh, in how many days will the entire work be finished?

Show answer & explanation

Correct answer: D

Explanation

The Correct answer is option 4 i.e. 1056\frac{5}{6}

Given that

Ramesh can complete a piece of work in 10 days

Suresh can complete the same piece of work in 12 days

Total work = LCM (10, 12) = 60

The efficiency of Ramesh = 60/10 = 6

The efficiency of Suresh = 60/12 = 5

If they are working on alternate days, starting with Ramesh

In 2 days, (6 + 5 = 11) work will be completed

In 10 days, 55 work will be completed

Now, the remaining work (60 - 55 = 5) will be completed by Ramesh in 5/6 days

Hence, the total work completed in 1056\frac{5}{6} days