SSC CHSL - 3 June 2022 - Shift 3 • Quantitative Aptitude • Q52

Ram and Shawan working together can complete a job in 5 hours, where as Ram alone can complete the same job in 6 hours. In how many hours can Shawan alone complete the job?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 30

Time taken by Ram and Shawan together to complete the work = 5 hours

Ram alone completes the work = 6 hours

Efficiency = Total work/No. of time taken

Let the total work be 30 units(we have taken L.C.M of 5 and 6)

Time taken by Ram and Shawan together = 5 hours

Efficiency of Ram and Shawan = 30/5 = 6 unit/hours

Ram alone takes 6 hrs.

Efficiency of Ram = 30/6 = 5 unit/hours

Efficiency of Shawan = ( 6 - 5) = 1 unit/h

Time taken by Shawan = 30/1 = 30 hours