SSC CGL 2023 PYQ — Question 70

SSC CGL - 25 July 2023 - Shift 1 • Quantitative Aptitude • Q70

Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 17.5 days.

Let the total work to be done (LCM of 5 and 7) be 35 units.

Efficiency of Raju and Rajat together = 35/5 = 7 units/day

Efficiency of Raju alone = 35/7 = 5 units/day

Efficiency of Rajat alone = 7 - 5 = 2 units/day

Time taken by Rajat alone = 35/2 = 17.5 days