SSC GD 2025 PYQ — Question 49

SSC GD Const 2025 (English) - 04 Feb 2025 - Shift 2 • Quantitative Aptitude • Q49

Rajeshwar can do a piece of work in 12 days, Vikram in 6 days and Tiger in 15 days. They all start the work together, but Rajeshwar leaves after 2 days and Vikram leaves 3 days before the work is completed. In how many days is the work completed?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e.   5575\frac{5}{7}.

total work = (LCM of 12,6,15) = 60 units.

Efficiency (units/day):

Rajeshwar = 60×(1/12) = 5

Vikram = 60×(1/6) = 10

Tiger = 60×(1/15) = 4

Together = 19 units/day.

First 2 days (all three): 2×19 = 38 units

Remaining = 60 − 38 = 22 units.

After 2 days Rajeshwar leaves. Let there be y days when Vikram+Tiger work, then last 3 days only Tiger works.

Vikram+Tiger rate = 10 + 4 = 14 units/day

So 22 = 14y + 3 × 4 = 14y + 12

→ 14y = 10

→ y = 5/7 day.

Total time = 2 + y + 3 = 5 + 5/7 =5575\frac{5}{7} days.