SSC CPO - 29 June 2024 Shift 2 • Quantitative Aptitude • Q147

Rajan and Rajat can do a work in 64 days and 48 days, respectively. Starting with Rajat, they work on alternate days. In how many days will the work be completed?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 543454{3\over4}.

Let the total work to be done LCM(64, 48) be 192 units.

Total work = Efficiency × Time

According to the given question,

Efficiency of Rajan = 19264192 \over 64 = 3 units/day

Efficiency of Rajat = 19248192 \over 48 = 4 units/day

Starting from Rajat, they work on alternate days, 

The work done by Rajat and Rajan in 2 days = 4 + 3 = 7 units

The work done by Rajat and Rajan in (2 × 27) 54 days = 189 units  (7 × 27)

Remaining work = 192 - 189 = 3 units

Now Rajat comes to work, 

Time taken by Rajat to complete 4 units of work = 1 day

Time taken by Rajat to complete 3 units of work = 14×3{1 \over 4} \times 3 = 343 \over 4 days

The total time taken by them to complete the work = 543454 {3 \over 4} days

Hence the work will be completed in 543454 {3 \over 4} days.