Rajan and Rajat can do a work in 64 days and 48 days, respectively. Starting with Rajat, they work on alternate days. In how many days will the work be completed?
Show answer & explanation
Correct answer: B
Explanation
The correct answer is option 2 i.e. .
Let the total work to be done LCM(64, 48) be 192 units.
Total work = Efficiency × Time
According to the given question,
Efficiency of Rajan = = 3 units/day
Efficiency of Rajat = = 4 units/day
Starting from Rajat, they work on alternate days,
The work done by Rajat and Rajan in 2 days = 4 + 3 = 7 units
The work done by Rajat and Rajan in (2 × 27) 54 days = 189 units (7 × 27)
Remaining work = 192 - 189 = 3 units
Now Rajat comes to work,
Time taken by Rajat to complete 4 units of work = 1 day
Time taken by Rajat to complete 3 units of work = = days
The total time taken by them to complete the work = days
Hence the work will be completed in days.