SSC CGL 2023 PYQ — Question 56

SSC CGL - 18 July 2023 - Shift 2 • Quantitative Aptitude • Q56

Raja and Rocky together can complete painting work in 5 days. Together, they both start painting, but after 2 days, Rocky falls sick and leaves the work. If Raja completes the remaining painting in 4 days, find the number of days in which Rocky alone can do the work.

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 20 days.

Given:

Raja and Rocky, together, can complete painting work in 5 days

Calculations:

Let the efficiency of Raja and Rocky be X and Y

According to the question;

⇒ 2(X + Y) + 4X = 5(X + Y)

⇒ 2X + 2Y + 4X = 5X + 5Y

⇒ X = 3Y

⇒ X/Y = 3/1

Total work = 5 × (3 + 1) = 20

Hence, Rocky alone can do the work in = 20/1 = 20 days