R is 40 percent more efficient than S. S alone can finish a work in 35 days. In how many days will R alone finish the same work?
Show answer & explanation
Correct answer: C
Explanation
Efficiency of S = 100%
Efficiency of R = 140%
Time taken by R = 35 × 100/140 = 25 days