SSC GD 2026 PYQ — Question 55

SSC GD Constable - 30 April 2026 - Shift 3 • Quantitative Aptitude • Q55

R alone can do a work in 12 days working 4 hours a day. S alone can do the same work in 6 days working 8 hours a day. How many hours do they need to work together in a day to complete the same work in 4 days?

Show answer & explanation

Correct answer: B

Explanation

R's total work = 12 × 4 = 48 hours

S's total work = 6 × 8 = 48 hours

Total work = 48 units

Time required per day to complete the work in 4 days = 48 / (4 × 2)= 6 hours