SSC GD 2026 PYQ — Question 51

SSC GD Constable - 28 April 2026 - Shift 1 • Quantitative Aptitude • Q51

R alone can complete a work in 32 days. S alone can complete the same work in 40 days. They work together for 8 days. What part of total work is completed?

Show answer & explanation

Correct answer: C

Explanation

Work done by R in 1 day = 1/32

Work done by S in 1 day = 1/40

Total work done in one day = 1/32 + 1/40

= 5/160 + 4/160

= 9/160

Work done in 8 days = 8 × 9/160

= 72/160 = 9/20