Q and R together are 3 times as efficient as P. P and R together are 2.5 times as efficient as Q. Q and R together can complete a work in 60 days. P alone can complete the same work in how many days?

Show answer & explanation

Correct answer: B

Explanation

Let the efficiencies of P, Q, and R be p, q, and r, respectively.

Given:

Q + R = 3P

P + R = 2.5Q

Q + R = 1/60

3P = 1/60

P = 1/180

Therefore, P alone will complete the work in 180 days.