SSC CHSL 2024 PYQ — Question 73

SSC CHSL - 10 July 2024 - Shift 4 • Quantitative Aptitude • Q73

P completes a work in 12 days and Q in 24 days. In how many days P and Q working together can complete the same work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 8 days.

Let the total work to be done (LCM of 12 and 24) be 24 units.

According to the question,

Efficiency of P = 24/12 = 2 units/day

Efficiency of Q = 24/24 = 1 unit/day

Time taken by both of them to complete the work = 24/(2 + 1)

⇒ 24/3 = 8 days