SSC Selection Post 2022 PYQ — Question 54

SSC Selection Post - Matriculation Level - 10 Feb 2022 - Shift 1 • Quantitative Aptitude • Q54

P can do a piece of work in 48 days, and Q can do half of the same work in 30 days. If they both work together, in how many days can they complete three-eighths of the work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 10.

Time taken by P to complete the whole work = 48 days

Time taken by Q to complete the whole work = 30 × 2 = 60 days

LCM(48, 60) = 240

The efficiency of P = 240/48 = 5 units

The efficiency of Q = 240/60 = 4 units

Time taken by both to complete three-eighths of the whole work = 38×2409{{3\over8}\times240}\over9 = 90990\over9 = 10 days