SSC CHSL 2023 PYQ — Question 69

SSC CHSL - 09 March 2023 - Shift 2 • Quantitative Aptitude • Q69

P and Q together can complete the work in 20 days. If Q alone can complete the work in 25 days, then in how many days can P alone complete the same work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2 i.e. 100 days.

Total work = 100 (LCM of 20 and 25)

Efficiency of P = (100/20) - (100/25) = 5 - 4 = 1 unit/day

Time required for P to complete the work = 100/1 = 100 days