SSC GD 2023 PYQ — Question 46

SSC GD Constable (English) - 31 Jan 2023 - Shift 2 • Quantitative Aptitude • Q46

P and Q together can complete a work in 21 days. Q alone can complete it in 84 days. If efficiency of Q becomes double, then in how many days approximately will P and Q together complete the work?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 17 days

Calculations:

Number of days taken by P + Q = 21

Number of days taken by Q = 84

Total work done (LCM of 21 and 84) = 84 units

Efficiency of P + Q = 84/21 = 4 

Efficiency of Q = 84/84 = 1

Efficiency of P = Efficiency of (P + Q) - Efficiency of Q

⇒ 4 - 1 = 3

According to the question;

Efficiency of Q is doubled = 2

Total new efficiency = 3 + 2 = 5

Required time taken = 84/5 = 16.8 

⇒ 17 days (Approximately)