SSC CPO 2020 PYQ — Question 146

SSC CPO - 24 Nov 2020 - Shift 2 • Quantitative Aptitude • Q146

P and Q can do the work together in 12 days. P alone can do the same work in 18 days. In how many days can Q alone complete two-thirds part of the same work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 24.

Time taken by P and Q to do the work = 12 days

P alone can do the work in 18 days

L.C.M(12 and 18) = 36 

The efficiency of P and Q = 36/12 = 3 units

The efficiency of P = 36/18 = 2 units

Thus,

The efficiency of Q = 3 - 2 = 1 unit

two-third part of the work = 2/3 × 36 = 24 units 

Time taken by Q = 24/1 = 24 days