SSC CGL 2022 PYQ — Question 64

SSC CGL - 01 Dec 2022 - Shift 1 • Quantitative Aptitude • Q64

P and Q can complete a project in 15 days and 10 days, respectively. They started doing the work together, but after 2 days, Q had to leave and P alone completed the remaining work. In how many days was the whole work completed?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is Option 2. i.e. 12 .

According to question,

(P + Q)'s 1 day's work = 1/15 + 1/10

⇒ (2 + 3)/30

⇒ 5/30

⇒ 1/6 

Work done by P and Q in 2 days = 1/6 × 2

⇒ 1/3

Remaining work = 1 - 1/3

⇒ 2/3

Now,

1/15 work is done by P in 1 day.

So, 2/3 work will be done by P in 15 × 2/3 = 10 days

So, the total time is taken = 10 + 2

⇒ 12 days