SSC CHSL 2023 PYQ — Question 75

SSC CHSL - 10 March 2023 - Shift 3 • Quantitative Aptitude • Q75

P alone can complete a piece of work in 10 days, while Q alone can complete the same piece of work in 15 days. To complete the work in 4 days, R is hired by P and Q. How many days does R take to complete the work alone?

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. 12 days.

Let R alone complete the work in x days

So, (1/10) + (1/15) + (1/x) = 1/4

⇒ (1/x) = (1/4) - (1/10) - (1/15) = (1/12)

⇒ x = 12

Hence, R takes 12 days to complete the work alone.