SSC CHSL 2024 PYQ — Question 62

SSC CHSL - 11 July 2024 - Shift 1 • Quantitative Aptitude • Q62

Nirmal completed the school project in 45 days. How many days will Amit take to complete the same work if he is 25% more efficient than Nirmal?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 36.

Let Nirmal's efficiency =100%

Amit's efficiency = 100% + 25% = 125%

Efficiency is inversely proportional to the time taken. If efficiency increases, time taken decreases.

Let the time required for Amit = x days

So, 100/125 = x/45

⇒ 4/5 = x/45

⇒ x = (4/5) × 45 = 36

Therefore, Amit will take 36 days to complete the same project.