SSC GD 2023 PYQ — Question 55

SSC GD Constable (English) - 16 Jan 2023 - Shift 1 • Quantitative Aptitude • Q55

M can do a piece of work in 12 days and N in 24 days. They begin together, but M leaves the work 6 days before the completion of the work. Find the total number of days to complete the entire work.

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 12 days.

M can do a piece of work = 12 days

N can do a piece of work = 24 days

Let's assume the total work = LCM of 12 and 24 = 24

Efficiency = Total work/Total time

So, efficiency of M = 24/12 = 2 unit per day

Efficiency of N = 24/24 = 1 unit per day

Their 6 days work = (2 + 1) × 6 = 18

Remaining work done by N = (24 - 18)/1 = 6 days

So, total days to finish the work = 6 + 6 = 12 days