M and R together can do a work in 18 days. R and P together can do the same work in 24 days. P and M together can do the same work in 36 days. In how many days can P alone do the same work?
Show answer & explanation
Correct answer: B
Explanation
SSC MTS - 19 Feb 2026 - Shift 1 • Quantitative Aptitude • Q18
M and R together can do a work in 18 days. R and P together can do the same work in 24 days. P and M together can do the same work in 36 days. In how many days can P alone do the same work?
Correct answer: B
Explanation