John does piece of work in 3 hours, Joe does of the remaining work in 1 hour and George finishes the remaining work in 5 hours. How long would it have taken the three working together to do the work?
Show answer & explanation
Correct answer: D
Explanation
The correct answer is option 4 i.e. hours.
John can do work in 3 hours so that he can complete the entire work in 6 hours.
Remaining work = 1 - 1/2 = 1/2
Joe does 1/4 of the remaining work i.e 1/8 work in 1 hour , So he can complete the entire work in 8 hours.
Now remaining work = 3/8
George finishes the remaining work in 5 hour.
George do 3/8 work in 5 hours ,So he can complete entire work in 40/3 hours.
If all three work together, then,
= 120/44 = 30/11
So, the answer would be option d) hours