SSC GD 2021 PYQ — Question 57

SSC GD Constable (English) - 7th December 2021 Shift 1 • Quantitative Aptitude • Q57

John can complete a piece of work in 6 days working 8 hours each day and Manu can complete it in 3 days working 4 hours each day. How long will they take to complete it, working together 9(3/5) hours a day?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 1 day.

Given:

John can complete a piece of work in 6 days working 8 hours each day

Manu can complete it in 3 days working 4 hours each day

Calculations:

Total amount of hours John worked = 48 hours

Total amount of hours Manu worked = 12 hours

Total work (LCM of 48 and 12) = 48 units

Efficiency of John = 48/48 = 1 unit

Efficiency of Manu = 48/12 = 4 units

Time required to complete the whole work in 9(3/5) hours per day = (48/(1 + 4) × 9(3/5))

= (48 × 5)/(5 × 48) = 1 day