Question: If P, Q, and R work together, how many days will they take to complete a project?

Statement I: Q and R together can complete the project in 10 days.

Statement II: P and R together can complete the project in 15 days.

Show answer & explanation

Correct answer: D

Explanation

The correct answer is option 4 i.e. Even when combined, the information in both Statement I and Statement II is not enough to answer the question.

We need the combined rate of P, Q, and R:

Statement I: Rate of (Q + R) = 1/10

Statement II: Rate of (P + R) = 1/15

Together, we still cannot find P + Q + R uniquely because the rate of R is unknown.

For example, if R is very fast, then P and Q are slower, but the sum changes.

Thus, even when combined, the information in both Statement I and Statement II is not enough to answer the question.