SSC Selection Post 2022 PYQ — Question 70

SSC Selection Post - Higher Secondary Level 2022 - 2 Aug 2022 - Shift 2 • Quantitative Aptitude • Q70

In a typing shop, Lalit can complete typing of a book in 9 days, while Amit can finish the same work in 8 days. How many days will they take together to complete the work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 4.23 days.

Let the total work to be done LCM(9 and 8) be 72 units.

Efficiency of Lalit = 72/9 = 8 units/day

Efficiency of Amit = 72/8 = 9 units/day

Time taken by Lalit and Amit together to complete the work = 72/(8 + 9)

⇒ 72/17 = 4.23 days