SSC CGL 2022 PYQ — Question 75

SSC CGL - 05 Dec 2022 - Shift 1 • Quantitative Aptitude • Q75

In 4/5 time, Naman can do half work of Gagan. When both of them are working together, then complete the entire work in 16 days. Find out the time taken by Gagan to complete the whole work alone.

Show answer & explanation

Correct answer: D

Explanation

The correct answer is Option 4 i.e. 26 days

Concept used:

Total work = Efficiency × time

Calculations:

Let the efficiency of naman and gagan ne N and G.

According to the question;

⇒ (N × 4)/1 = (G × 5)/2

⇒ N/G = 5/8

Total work = 16 × 13 units

Time taken by gagan = (16 × 13)/8 = 26 days