If P can complete 1/3 of a work in 6 days and Q can complete 1/4 of the same work in 9 days, how much will Q get if both work together and are paid in advance ₹210 in all?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is option 3 i.e. ₹70.
Calculations:
P complete 1/3rd of the work in 6 days
P complete whole work = 18 days

Similarly, Q can complete the whole work = 4 × 9 = 36
Total efficiency = 2 + 1 = 3
Amount of Q = (210/3) × 1 = 70