SSC GD 2021 PYQ — Question 64

SSC GD Constable (English) - 18th November 2021 Shift 3 • Quantitative Aptitude • Q64

If P can complete 1/3 of a work in 6 days and Q can complete 1/4 of the same work in 9 days, how much will Q get if both work together and are paid in advance ₹210 in all?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. ₹70.

Calculations:

P complete 1/3rd of the work in 6 days

P complete whole work = 18 days

Similarly, Q can complete the whole work = 4 × 9 = 36

Total efficiency = 2 + 1 = 3

Amount of Q = (210/3) × 1 = 70