SSC GD 2024 PYQ — Question 42

SSC GD Const (English) - 29 Feb 2024 - Shift 2 • Quantitative Aptitude • Q42

If D can do 10 percent of a work in 3 days, then D can complete the entire work in how many days?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 30 days.

D can do 10 percent of a work in 3 days

⇒ 10% of work = 3 days

Thus, D will complete 100% work in 

⇒ 10% × 10 = 3 × 10 = 30 days