SSC GD 2019 PYQ — Question 75

SSC GD Constable (English) - 13 Feb 2019 Shift 3 • Quantitative Aptitude • Q75

If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 15 days.

Undestanding/Application

C alone can complete two third part of a work in 12 days.

If a person can complete (x/y) part of a work in z days, then the person can complete the whole work in {z × (y/x)} days

2/3 part = 12 days

1 part = (12 × 3)/2 = 18 days

C can complete the whole work in 18 days.