If A works twice as fast as B, and A can complete a task in 10 days, how many days will it take for B to complete the task?

Show answer & explanation

Correct answer: D

Explanation

A's speed = 2 times B's speed

A completes the work = 10 days

If A : B = 2 : 1 (Speed)

Then the ratio of time = 1 : 2

A's time = 10 days

B's time = 10 × 2 = 20 days