SSC Stenographer 2025 PYQ — Question 65

SSC Stenographer - 07 Aug 2025 - Shift 1 • Reasoning • Q65

If 6 workers complete a job in 15 days. How many days will 9 workers take assuming the same work rate?

Show answer & explanation

Correct answer: A

Explanation

Work is fixed, so:

Workers × Days = Total Work

6 × 15 = 90

Now for 9 workers:
Days = Total Work ÷ Workers

90 ÷ 9 = 10 days

Hence, the correct option is 1.