If 6 men can complete a work in 16 days, how many men are required to complete the same work in 12 days?
Show answer & explanation
Correct answer: C
Explanation
Total work = 6 × 16 = 96 man-days
Now, the work is to be completed in 12 days, so the required number of men = 96 ÷ 12 = 8 men.