If 50 men working 8 hours a day can complete a work in 20 days, then in how many days will 32 men working 10 hours a day complete the same work?
Show answer & explanation
Correct answer: B
Explanation
The correct answer is option 2 i.e. 25.
According to the given question,
50 × 8 × 20 = 32 × 10 × D
⇒ D = 25 days