SSC Selection Post 2022 PYQ — Question 67

SSC Selection Post - Matriculation Level - 3 Feb 2022 - Shift 2 • Quantitative Aptitude • Q67

If 50 men working 8 hours a day can complete a work in 20 days, then in how many days will 32 men working 10 hours a day complete the same work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 25.

According to the given question,

50 × 8 × 20 = 32 × 10 × D

⇒ D = 25 days