SSC Stenographer 2025 PYQ — Question 76

SSC Stenographer - 07 Aug 2025 - Shift 1 • Reasoning • Q76

If 4 workers can complete a task in 8 days. How many days will 8 workers take to complete the same task?

Show answer & explanation

Correct answer: B

Explanation

Work(constant) = Workers × Days

4 × 8 = 32 worker-days

For 8 workers:
Days = 32 ÷ 8 = 4 days

Hence, the correct answer is option 2.