If 4 workers can complete a task in 8 days. How many days will 8 workers take to complete the same task?
Show answer & explanation
Correct answer: B
Explanation
Work(constant) = Workers × Days
4 × 8 = 32 worker-days
For 8 workers:
Days = 32 ÷ 8 = 4 days
Hence, the correct answer is option 2.