SSC CPO 2023 PYQ — Question 116

SSC CPO - 03 Oct 2023 - Shift 3 • Quantitative Aptitude • Q116

If 4 men or 6 boys can finish a piece of work in 20 days, then in how many days can 6 men and 11 boys finish the same work?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 6.

Given that

If 4 men or 6 boys can finish a piece of work in 20 days

Let the efficiency of a man and a boy be M and B respectively

6 men and 11 boys finish the same work in D days

Concept used

Work =  time × efficiency

According to the question

4M × 20 = 6B = 20

M/B = 3/2

Total work = 4 × 3 × 20 = 240

Hence, the required time D = 240/(6 × 3 + 11 × 2) = 240/(18 + 22) = 240/40 = 6 days