SSC CPO 2022 PYQ — Question 130

SSC CPO - 9 Nov 2022 - Shift 1 • Quantitative Aptitude • Q130

If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 50

Given that

If 25 persons can complete a work in 140 days

Let 'M' persons can complete the work in 70 days

According to the question

⇒ 25 × 140 = M × 70

⇒ M = 50