If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?
Show answer & explanation
Correct answer: B
Explanation
The correct answer is option 2 i.e. 50
Given that
If 25 persons can complete a work in 140 days
Let 'M' persons can complete the work in 70 days
According to the question
⇒ 25 × 140 = M × 70
⇒ M = 50