If 24 people can build 90 identical walls in 25 days, then how many more days will 27 people require to build 162 such walls?
Show answer & explanation
Correct answer: C
Explanation
The correct answer is Option 3 i.e.15.
Given that
24 people can build 90 identical walls in 25 days
Formula used
( M1 × D1 ) / W1 = ( M2 × D2 ) / W2 ; where m = number of men, d = number of days worked, w = work done
Hence,
Solving for D we get
D = 40
Hence the number of extra days required = 40 - 25 = 15 days.