If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
Show answer & explanation
Correct answer: D
Explanation
The correct answer is option 4 i.e. 16.
Total work to be done = 15 × 16 × 8 units
Required number of days = 15 × 16 × 8/(10 × 12)
⇒ 16 × 1 = 16 days