SSC CGL 2021 PYQ — Question 65

SSC CGL - 20 Aug 2021 - Shift 1 • Quantitative Aptitude • Q65

Fourteen persons can do a work in 18 days, After 5 days of work, 6 workers left the work, and joined back on the last day of the work. In how many days the work got completed?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is option 1 i.e. 27.

Let the efficiency of 1 man = 1 unit/day

Total work = 18 × 14 = 252 units

Work done in 5 days = 5 × 14 = 70 units

Remaining work = 252 - 70 = 182 units

No of workers left = 14 - 6 = 8

Let the remaining work can be completed in 'n' days so,

⇒ 8(n - 1) + 14 × 1 = 182

⇒ 8n = 182 - 6

⇒ 8n = 176

n = 22 days

Total working days = 22 + 5 = 27 days