SSC GD 2025 PYQ — Question 58

SSC GD Const 2025 (English) - 13 Feb 2025 - Shift 3 • Quantitative Aptitude • Q58

Fifty-four men can complete a work in 48 days. After 8 days of working, thirty-six more men joined them. How many days will they now take to complete the remaining work?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is option 3 i.e. 24.

Total work = 54 men × 48 days = 2592 man-days

Work done in first 8 days =54 men × 8 days = 432 man-days

Remaining work = 2592 - 432 = 2160 man-days

New workforce = 54 + 36 = 90 men

Days to finish remaining work = 2160 ÷ 90 = 24 days