SSC CGL 2021 PYQ — Question 53

SSC CGL - 13 Aug 2021 - Shift 2 • Quantitative Aptitude • Q53

Eighteen persons working 8 hours a day can complete 3 units of work in 10 days. How many days are required by 25 persons to complete 5 units of work working 6 hours a day?

Show answer & explanation

Correct answer: B

Explanation

The correct answer is option 2 i.e. 16

Work = men × days × hours × 1/units of work

⇒ (18 × 8 × 10)/3 = (x × 25 × 6)/5

⇒ x = 16 persons