C alone can complete a work in 50 days and D alone can complete the same work in half of the time taken by C. In how many days will both together complete 3/10 part of the total work ?
Show answer & explanation
Correct answer: B
Explanation
The correct answer is option 2 i.e. 5 days.
Rate of C = 1 / 50 work/day
D's rate of work:
⇒50 / 2 = 25 days
Rate of D = 1 / 25 work/days
Combined rate = 1 / 50 + 1 / 25
⇒
Time =