SSC GD 2023 PYQ — Question 41

SSC GD Constable (English) - 11 Jan 2023 - Shift 3 • Quantitative Aptitude • Q41

Bhanu can do a work in 10 days. Ramesh takes 12 days to complete it. Rohit takes as long as Bhanu and Ramesh would work together. How long will it take Ramesh and Rohit to complete the work together?

Show answer & explanation

Correct answer: C

Explanation

The correct answer is Option 3 i.e. 3343\frac{3}{4}days.

Bhanu can do the work in 10 days, so his one-day work = 1/10 units 
Ramesh can do the work in 12 days, so his one-day work = 1/12 units 

Rohit takes as long as Bhanu and Ramesh working together, so their combined work rate is:

1/10 + 1/12 = (12 + 10)/120 = 22/120 = 11/60 units/day

Now, to find out how long it will take Ramesh and Rohit to complete the work together, we can add their work rates:

To complete the entire job, it will take them 1 divided by their combined work rate:

1/(4/15) = 15/4 = 3.75 = 3343\frac{3}{4} days